Project Summary
The Phase IV expansion of Pioneer Generation Station adds 583 MW to the existing facility by integrating simple-cycle combustion turbines and reciprocating engines to support load growth. The two technologies are being installed parallel, a half-mile apart, at either end of the existing facility.
Basin Electric selected AZCO and Burns & McDonnell to engineer, procure and construct (EPC) its largest single-site generation plant since the 1980s.
The EPC team effort with Burns & McDonnell established upfront project development efforts, including environmental permitting, collective initial planning, and responsive decision-making to support the engineering, procurement, construction and startup/commissioning professionals on the project.
Our construction scope includes mechanical installation of a series of 18-MW Wartsila W18V50SG reciprocating engines and two 240-MW Siemens STG6-PAC-5000F combustion turbines.
We are installing all the below-grade utilities including piping, tank setting, and electrical duct banks. The above-ground scope consists of structural steel erection, inlet filters, centerline equipment installation, exhaust ductwork and stacks, electrical equipment setting, tank setting, electrical raceway installation, cable/wire pulling and terminations, instrumentation, and miscellaneous balance-of-plant (BOP) equipment setting associated with piping.
Metal Prefabrication Scope
- 2,100 unique pieces
- 850 unique assemblies
- 15,461 separate parts
- 153,000 pounds of fabricated steel delivered
- Prioritized fabrication sequencing
- Collaboration with site and pipe fabrication
Pipe Prefabrication Scope
- More than 3,000 unique pieces of HDPE, carbon steel and stainless steel pipe
- More than 33,000 linear feet of carbon steel and stainless steel pipe
- Pipe diameters ranging from a half-inch to 24 inches