SOLUTION
After a thorough analysis of plans for the new facility, we designed a sequential construction plan that addressed all of Green Bay Packaging’s pain points. To help keep construction on schedule, we utilized our just-in-time process in the prefabrication shop to get the piping to the project site right before it was needed for construction. This helped optimize the spacing required for the pipe laydown area and minimized the cluster of pipes in the field, waiting to be installed.
At peak staffing, roughly 130 pipefitters and six equipment operators worked day and night shifts, maintaining consistent coordination between the prefabrication and field teams to keep the project on schedule.